Planning and building rules for school outdoor classrooms
Most outdoor classrooms in England go up without a full planning application, because schools have their own permitted development rights. Those rights come with limits, and the limits are worth knowing before you choose a spot.
Class M in one picture
Class M, in Part 7 of Schedule 2 to the General Permitted Development Order 2015, lets schools in England put up new buildings without applying for planning permission, as long as they stay inside its limits. Height and distance are the two that most often decide where an outdoor classroom can go.
Put simply: the closer to the edge of the site, the lower it has to be, and if there are homes over the fence you need to keep 5 m away altogether.
The footprint cap
The 2021 amendment changed how much a school can add. The total footprint of buildings put up under Class M since 21 April 2021 must stay within 25% of the footprint of the school's buildings as it was on that date, or 250 m², whichever is greater.
So a small school whose buildings covered 600 m² still gets 250 m², because 25% of 600 m² is only 150 m². A larger school with 2,000 m² gets 500 m². Anything added since April 2021, a new classroom block or an earlier shelter, comes out of the same total. Our cost and size planner does the sum for you.
Nurseries are different
This one is easy to miss. The High Court has held that a nursery is not a "school" for Class M. If you run a standalone nursery or pre-school, you can't lean on Class M; ask the council what you need before you commit.
Other Class M conditions
Class M has more conditions than the ones drawn above, and some sites have extra protections. It's very important to ask the council, or the planning adviser your trust uses, to confirm before you sign an order. A short email with a site plan and the drawings usually gets a clear answer.
Wales and Scotland
Class M is part of the permitted development order for England. Schools in Wales and Scotland have their own rules, so start with the council's planning team.
Building Regulations
Planning and Building Regulations are separate. Schedule 2 of the Building Regulations 2010 exempts some small detached buildings, depending on floor area, whether anyone sleeps there, distance from the boundary and the materials. An open shelter and a class-sized enclosed room can land on different sides of that line, so ask the builder to say in writing whether building control will be involved and who applies.
Safety while it is built
When the school has building work done, it is the client under the Construction (Design and Management) Regulations 2015, with duties of its own. In practice that means choosing a competent builder, agreeing how the work area is fenced off from pupils, and making sure sign-in and safeguarding rules are followed. Many schools time the noisy work for a holiday.
Size: the DfE's area guidelines
The DfE's area guidelines for mainstream schools (BB103) set out the space schools are expected to plan for indoors. They are guidance rather than law, but they are a sensible reference if an enclosed outdoor room will be used as a full classroom.
Sources for the figures on this page
- The Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2, Part 7, Class M
- The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) Order 2021, article 9
- High Court judgment [2019] EWHC 14 (Admin) on nurseries and Class M
- The Building Regulations 2010, Schedule 2: exempt buildings and work
- HSE: Construction (Design and Management) Regulations 2015
- DfE: Area guidelines for mainstream schools (BB103)
Planning questions in brief
Do schools need planning permission for an outdoor classroom?
Often not in England, because Class M permitted development covers new school buildings within limits on height, distance from homes and total footprint. Check with the council before you order.
What is the height limit?
5 m if any part is within 10 m of the site boundary, 6 m elsewhere.
How close can it be to houses?
No part can be within 5 m of a boundary where the land next door is in residential use.
Does Class M cover nurseries?
No. The High Court has held that a nursery is not a school for Class M, so standalone nurseries should ask the council.
What about Wales and Scotland?
Class M is part of the order for England. Schools in Wales and Scotland should ask their council what applies.
Who is responsible for safety while it is built?
Under the Construction (Design and Management) Regulations 2015 the school, as the organisation having the work done, is the client and has duties of its own. The HSE's CDM pages explain them.
Ask for quotes for your school
We find an outdoor classroom builder who works in your area and give you their name before any of your details go to them. It costs your school nothing.
- You choose. The builder only hears from you once you have said yes.
- Written prices. Ask for the base, drawings and any electrics to be priced line by line.
- No obligation. Getting a price commits the school to nothing. How it works
Thank you, that has reached us.
Here is what happens next.
- We look for an outdoor classroom builder who works in your area and suits the brief.
- We email or phone you with their name. Your details go to them only if you say yes.
- They arrange a site visit and send the school a written quote.